Some Key Features of the SOP Act NSW
Following is an outline description of some key features of the Act followed by a reference to the part of the Act that contains the full description of each feature.
Note: Readers should not rely upon the abbreviated details listed below but should refer to the relevant section of the Act for a more complete description of each feature.
- The object of the Act is set out in S3
- The Act defines the term "construction work" for which the payment claims may be submitted under the Act in S5
- The Act also applies to "related goods and services" as defined in S6
- The Act does not apply to a construction contract for the carrying out of residential building work. See S7(b)
- Rights to Progress Payments and a description of a ‘reference’ date is set out in S8
- The due date for payment of a Payment Claim is set out in S11(1A) for a head contractor and S11 (1B) for a subcontractor. • Note: Payment times are different for a head contractor and a subcontractor see S11 (1a) & S11 (1b)
- A "Pay when Paid" provision of a Contract does not apply to Payment Claims made under the Act. Any such provision in a Contract offends the Act. See S12
- The provisions of the Act have effect despite any provisions to the contrary in any Contract. That is, parties to a Contract cannot contract out of the provisions of the Act. See S34
- To be valid, Payment Claims must meet the requirements of Division 1,S13 of the Act. Payment Schedules, must meet the requirements of S14 of the Act.
- The Act prescribes time limits relative to:
- The submission of a Payment Claim. Refer S13
- The provision of a Payment Schedule. Refer S14
- The submission of an Adjudication Application. Refer S17
- The submission of an Adjudication Response. Refer S20
Note: Refer to the flowcharts, elsewhere on this website, and express provisions of the Act for further details.
- Time limits prescribed by the Act are expressed as business days, a definition of which is given in S4 of the Act.
- The Claimant may serve a Payment Withholding Request on the
Principal at any time after lodging an Adjudication Application. see S26A) and S26 (B) for details of the process under the Act.
- The serving of Notices under the Act is set out in S31
- Subject to certain pre-conditions and required notice to the Respondent a Claimant may suspend work under a contract see Division 3, S7 for details
|